Wonder Valley Data Centre: New Environmental Applications Raise Questions About Power, Water and Public Oversight
Two environmental applications for the proposed Wonder Valley data centre development south of Grande Prairie put the project's proposed power generation, Smoky River water supply and wastewater treatment systems under scrutiny. The applications come as Sturgeon Lake Cree Nation pursues three judicial reviews involving the project and provincial decisions. The central questions are what environmental protections will be required, how the public can participate and what approvals remain outstanding.
Back on top · first published Nov 9
Public Invited to Question Wonder Valley Developer Tuesday Evening
Peace Country residents will have an opportunity to hear directly from a senior executive of O'Leary Digital on Tuesday, November 10, as questions continue about the proposed Wonder Valley data centre development.
The Wapiti Area Synergy Partnership (WASP) is holding its November public meeting and annual general meeting at the Philip J. Currie Dinosaur Museum near Wembley.
Meeting details:
- Date: Tuesday, November 10, 2026
- Time: 7–9 p.m.
- Location: Philip J. Currie Dinosaur Museum, 9301 112 Avenue
- Admission: Free and open to the public
- Speaker: Zach Parston, Chief Operating Officer, O'Leary Digital
- Presentation: Wonder Valley
The meeting provides an opportunity for residents, landowners and other interested people to ask questions about the proposed development.
With environmental applications now identifying substantial power generation and water infrastructure, residents may want to ask about Smoky River withdrawals, wastewater discharge, air emissions, waste heat, Indigenous consultation and the long-term financial responsibilities associated with the project.
The gathering is not a formal regulatory hearing, and attending does not replace submitting a written statement of concern through Alberta's environmental application process.
A Major Development Faces Environmental Questions
The proposed Wonder Valley data centre development in the MD of Greenview is entering another stage of environmental scrutiny.
A public notice issued by O'Leary Digital Limited identifies two applications under Alberta's Environmental Protection and Enhancement Act.
One concerns construction and operation of a major power generation facility. The other concerns the water supply, treatment and wastewater systems required to support the proposed industrial development.
The notice identifies the Greenview Industrial Gateway, south of Grande Prairie, as the project area.
The applications raise questions about the project's environmental footprint, the amount of water required, how wastewater would be managed and the conditions regulators might impose.
An application does not establish that construction or operation has been approved.
A Proposed Power Plant With a Capacity of 9,166 Megawatts
The power application, identified as 001-512029, describes a proposed power plant with a capacity of 9,166 megawatts, including backup generation.
That is an enormous proposed generating capacity, but it should not be confused with the electricity demand of the data centres themselves.
Generating capacity, actual electricity consumption and the amount of electricity available at any particular time are different measurements.
The notice also does not establish how much power would be generated during normal operation or the eventual emissions from the facility.
Important questions include:
- How much natural gas would the power plant consume?
- What are the projected greenhouse gas and other air emissions?
- What emission controls and monitoring requirements would apply?
- Would the generating facilities operate continuously or in stages?
- How would waste heat be managed?
The answers depend on the technical application and the conditions imposed by regulators.
The Smoky River and the Water Question
The second application, 001-511808, concerns the construction, operation and reclamation of the Wonder Valley waterworks system.
The notice describes facilities associated with water withdrawal from the Smoky River, water treatment, storage and wastewater management.
These systems would support the industrial development and provide treated water for the data centre and power plant.
The notice refers to treatment processes including filtration, disinfection and wastewater treatment before discharge.
The distinction between water withdrawn, water consumed, water recycled and water returned to the watershed is particularly important.
A facility can withdraw substantial quantities of water while returning some of that water to the environment. The quantity, quality and timing of those returns determine much of the actual environmental impact.
The public needs clear figures showing expected daily and annual withdrawals, net consumption, wastewater discharge volumes and the protections that would apply during periods of low river flow.
Three Legal Challenges Add to the Scrutiny
Sturgeon Lake Cree Nation is pursuing three judicial reviews related to the project and provincial decisions.
The proceedings concern a water licence, Alberta's decision not to require a provincial environmental impact assessment report, and the classification of Indigenous consultation.
The Nation has raised concerns about consultation and the potential effects of the development on its rights and interests.
The developer maintains that the project remains subject to applicable environmental approvals and that regulatory requirements must still be met.
These proceedings have not established that the challenged government decisions were unlawful.
An August 2026 court ruling allowed the water-licence judicial review to continue but did not determine the underlying consultation dispute or overturn the licence.
The underlying water-licence hearing has been reported as scheduled for December 2026.
How Can Residents Participate?
The environmental application notice provides an opportunity for people who believe they may be directly affected to submit written statements of concern to Alberta Environment and Protected Areas.
The notice specifies a 30-day period from its publication date.
A statement should identify the applicant, the relevant application number, the person's connection to the affected area and the particular environmental concerns.
The exact submission deadline must be calculated from the notice's original publication date, which has not yet been independently established.
Residents can review Alberta's public notices and application information through the provincial regulatory system.
The Questions That Still Need Answers
Several issues remain unresolved in the publicly reviewed information.
What is the final expected electricity demand, compared with the much larger proposed generating capacity?
How much water would be permanently consumed rather than returned to the Smoky River?
What would happen to withdrawals during drought or unusually low river flows?
How would the combined environmental effects of power generation, data processing, cooling, wastewater and future expansion be evaluated?
What financial security would be required for reclamation if the development were abandoned or its operators became insolvent?
And how much of the economic benefit would remain in Greenview and the surrounding Peace Country?
These are questions for regulators, the developer and public decision-makers. They are not, by themselves, evidence of wrongdoing.
Swan City Speaks
Should a data centre development of this scale require a comprehensive environmental impact assessment covering the entire project, rather than separate reviews of individual facilities?
Should residents have access to the project's projected water consumption, emissions and reclamation obligations before major approvals are granted?
And what assurances would give Peace Country residents confidence that the economic benefits justify the environmental and infrastructure commitments?
References
- O'Leary Digital Limited — Public Notice of Application, EPEA applications 001-512029 and 001-511808 (supplied public notice).
- Alberta Environment and Protected Areas — Public Notices
- MD of Greenview — Wonder Valley Project Newsletter
- Alberta Data Centre Watch — Wonder Valley Project Records
- Windspeaker reporting on the water-licence judicial review